Five Questions to Ask Before Your Data Center Migration
The five hard questions every operations leader should answer before committing to a data center migration, drawn from 200+ real projects.
A data center migration is rarely about the move itself. It is about the decisions you make in the six weeks before anything is unracked. The teams that get migration right almost always answer the same five questions first — and the ones that struggle skip past at least one of them.
1. What is the REALcost of an hour of downtime?
Most teams have a number from finance. Very few have a number from the customer journey. The gap between those two figures is where migration risk lives.
Why this matters
76%
Of migrations exceed their planned cutover window
Source: Uptime Institute 2024
4.2x
Higher incident rate in the 30 days post-cutover
Source: Internal benchmark, 212 projects
2. Who owns the rollback decision?
If the answer is a committee, you do not have a rollback plan — you have a meeting. Name a single person, write their phone number on the runbook, and rehearse the call.
3. Have you actually inventoried what is in the racks?
Your CMDB is wrong. It is always wrong. Plan a physical walk-through with photos and serials before quoting any vendor.
4. What does success look like at T+30 days?
Cutover is not the finish line. Define the SLOs you expect to hit a month later — latency, error rate, ticket volume — and the team that owns each one.
5. Are you migrating, or are you modernising?
Doing both at once doubles the risk and triples the timeline. Pick a lane, ship it, and revisit modernisation from a stable baseline.
Need a second pair of eyes on your migration plan?
We have run 200+ migrations across three continents. Book a 30-minute review and we will tell you what we would change.
Talk to a vetted data center partner
Get matched with pre-screened migration, relocation and decommissioning specialists. No spam, no obligation.